By Srikanth Murugan, Global Director Sales Engineering, Flexenclosure

flexDeveloped by The Green Grid, PUE (Power Usage Effectiveness) is a very useful metric for measuring the energy efficiency of a data centre. PUE is simply calculated by dividing the overall power entering the facility by the power consumed by the IT load within it – the target being to get as close as possible to a PUE of 1.0, as this would mean the data centre is 100 per cent efficient.

Designing data centres for low PUE and measuring actual performance is becoming increasingly important, as operators seek to minimise their environmental impact and reduce their operating costs. One of the results of this trend is that it is now nigh on impossible to find a data centre vendor that does not brag about its products’ exceptional PUE performance. But rather than accepting these marketing claims at face value, here are five important questions you need to ask to make sure that you’re getting the full energy efficiency story:

 

  1. Where is the power being measured?

The result of a PUE calculation can be highly variable depending on where the incoming power and IT load are being measured.  For a data centre the overall facility power should be measured at the incoming MLVDB (Main Low Voltage Distribution Board) and the IT load at the rack PDU’s. However, some vendors measure their IT load at the sub distribution boards, thus achieving a better looking PUE because they have ignored all the cable loss from the low voltage distribution boards to the racks. The table below summarises the four recommended categories for the measurement of PUE. Of course the ultimate PUE calculated and claimed for any given facility will vary depending on which measurement category is used.

 

  PUE Category 0* PUE Category 1 PUE Category 2 PUE Category 3
IT Energy Measurement Location UPS Output UPS Output PDU Output Server Input
Definition of IT Energy Peak IT Electric Demand IT Annual Energy IT Annual Energy IT Annual Energy
Definition of Total Energy Peak Total Electric Demand Total Annual Energy Total Annual Energy Total Annual Energy

* For PUE category 0 the measurements are electric demand (kW).

 

  1. Are all losses taken in to consideration?

When calculating a data centre’s PUE, you need to make sure all losses are taken in to consideration.  Unfortunately some vendors omit some losses from their calculations in order to achieve a much better efficiency figure, so you need to be sure they are including all losses in the switchgear, cables, lighting and UPS, as well the increased load on the cooling systems dealing with heat generated by the sun outside or even by the people inside the facility. Only then will you arrive at a realistic PUE for your facility.  For more on this, here is a very interesting article on Google’s approach to measuring PUE in their data centres.

 

  1. Is PUE a one-time calculation?

The amount of energy a data centre needs will vary over time depending on a number of factors. For example, an increased reliance on cooling systems during warmer weather will mean that PUE values are generally higher during the summer than the winter. So rather than making it a one-time calculation, PUE ideally needs to be calculated over the entire year to find the annual average as well as the annual peak. And from an operational cost planning perspective, accurately calculating this worst case figure is actually more important than knowing the best case scenario.

 

  1. Do local weather conditions affect PUE?

Most vendors like to claim PUE values of 1.1 or 1.2 for their data centres and this is of course entirely possible if the facility is deployed in a cold environment like the Nordics where free air cooling can be used very effectively. However, if you are building a data centre in the tropics your best case PUE is going to be around 1.5 to 1.6, so you need to make sure that the PUE value that any vendor is offering is based on the location where it is going to be built. Ask if they have done any modelling based on the weather patterns of the actual site location. Even if they have not built one there before, peak and average PUE can be accurately determined using statistical climate data (temperature and humidity) with simulation software.

 

  1. Will a vendor guarantee the PUE they claim?

All of the above said and given that it is relatively easy to manipulate PUE calculations so that the resulting values look better than they really are, possibly the most important question you can ask any vendor with regards their PUE claims is whether they will guarantee that level of performance over time? (At Flexenclosure we are ready to guarantee the PUE for every data centre we build, wherever it is in the world.)

Armed with these five questions, you should be able to cut through the marketing hype and compare competing vendors on a relatively level PUE playing field. Of course the economics of PUE is another subject altogether – the impact on PUE, for example, if powering a facility from the grid or with diesel or both, or the impact on PUE of increasing a facility’s redundancy level. That will have to be the subject for another article…