Originally posted on Sabey Data Centers.

Following the successful full lease-up of our first data center at our Round Rock, TX campus, we wanted to share a brief construction update on SDC AustinBuilding B.
Construction is now well underway, with the primary concrete structure rising and vertical construction clearly progressing. The project is tracking to schedule, and site activity has ramped up significantly as we move through early structural milestones.

Building B Highlights:

  • 54MW of total capacity, powered by an onsite substation
  • Fully secured utility power for the entire facility
  • Liquid cooling optimized design to support next-generation workloads
  • 6 data halls, each offering 30,000 SF of space

You can view a short video of our construction progress here.