TL;DR

  • Grid connection timelines do not match AI data center deployment schedules, creating a multi-year gap where facilities are ready in two to three years while utility interconnection can take up to seven years.
  • Data center electricity demand is rapidly climbing, projected by Lawrence Berkeley National Laboratory to increase from 4.4% of U.S. electricity in 2023 to between 6.7% and 12% by 2028.
  • Developers are actively leveraging on-site primary generation, phased energization, demand flexibility, and repurposed sites with existing headroom to bridge the gap until grid power arrives.
  • Power strategy must be prioritized from day one as a foundational design input alongside land and fiber, rather than treated as a late-stage procurement task

# # #

By Sean Hughes, Business Development Manager, Wärtsilä Energy

Everyone wants to talk about AI. Very few people want to talk about the one thing that decides whether any of it actually gets built: power. Not cooling. Not chips. Not even land. Power.

More specifically: when can I get it, and how much? A lot of projects start with a conversation that goes something like this: “We’ve got the land. We’ve got the tenant. The utility says 2031. Can you help?”

Developers can line up the site, the capital and the tenant. What they increasingly can’t line up is a grid connection that matches their schedule. That’s the conversation dominating the U.S. market right now, and it’s changing how data centers get planned, financed and delivered.

Two clocks, running at different speeds

Here’s the core problem. A hyperscale or AI campus can go from site selection to ready-for-load in two to three years. The grid infrastructure to serve it runs on a completely different clock.

New transmission takes the better part of a decade to plan, permit and build. Large transformers and switchgear have long lead times. Across the United States, developers are being quoted multi-year waits for large new loads. In response, grid operators in PJM, ERCOT, MISO and SPP are rewriting the rules for how those loads are studied and connected.

Meanwhile, demand keeps climbing. Lawrence Berkeley National Laboratory estimates data centers used about 4.4% of U.S. electricity in 2023 and could reach somewhere between 6.7% and 12% by 2028. Utilities haven’t planned for load growth like this in a generation.

I want to be fair to the utilities here. They have to protect every other ratepayer from paying for capacity that never gets used, and their queues are full of speculative requests. Nobody’s doing anything wrong. It’s a system built for slow, steady growth running into a step change.

But a developer with a tenant waiting doesn’t have seven years. And the tenant definitely doesn’t.

What developers are actually doing about it

My view is simple: waiting on the grid is not a strategy. When the grid date and the build date don’t line up, there are really four levers to pull. The best projects I see pull more than one.

Phase it. A partial connection now is often available sooner than a full one later. Build the campus to energize in stages and get revenue flowing while the rest catches up.

Be flexible. A data center that can reduce its demand on the grid for a limited number of hours each year can be much easier to connect.

Utilities and grid operators are starting to reward that.

Bring power on site. Dispatchable generation on site can carry part or all of the load until the grid arrives, then shift into a different role once it does.

Rethink the map. Sites with existing headroom, retired power plant sites with interconnection rights still attached, and locations near new generation are worth a lot more than they were a few years ago.

Primary power isn’t backup power

This is where I see the most confusion.

Backup generation is the spare tire. It sits in the trunk and you hope you never need it. Primary power is the engine. It runs every day, carrying the load as the main source of supply. Those are completely different problems, with different equipment, different economics and different operations. Plenty of developers are facing the primary power question for the first time, and it pays to treat it that way.

And going with primary power doesn’t mean walking away from the grid. Fully islanded campuses have to carry all of their own redundancy and reserve margin, and they give up the resilience a big interconnected system provides. I think of the better approach as a macro-grid: dependable power on site that can run the campus on its own, then connect to the grid when the timing makes sense. Once connected, explore opportunities to export power, benefiting both communities and data centre operators. The added capacity lowers electricity prices while giving operators an additional revenue stream.

The smarter play is building enough power for what the data center needs today, and designing in the flexibility to be part of the grid tomorrow. That’s not a sales line. It’s an engineering reality. On-site capacity that can flex down at peak, or support the system when it’s tight, changes the whole relationship. The result? A data center that’s a grid asset, not a grid problem. And a large load that can flex, is one that utilities are far more willing to connect.

Will it be on when you need it?

Developers don’t want a spec sheet, they want answers to two questions: will it be on when we need it, and can you fix it if it’s not?

That second question is going to matter more than people think. A lot of new players are winning U.S. data center work right now. Not all of them have the field technicians, parts and service coverage in place to back it up. A primary power plant is only as reliable as the people and parts behind it. Ask about that before you sign, not after your first outage.

Fuel deserves the same scrutiny. Whatever you build will likely run for decades. Fuel flexibility, predictable operating costs and getting the most out of every unit of fuel all add up to cost certainty over the life of the asset. That’s good business, and it’s good stewardship of resources.

Put power first

If I could give developers one piece of advice, it would be this: stop treating power as a procurement task that starts after the site and design are locked in. By then, your options have narrowed and your schedule is already at risk.

Power belongs at the very start of the plan, right alongside land and fiber. Talk to the utility before you commit to a site, and treat its realistic timeline as a design input. If on-site generation will carry load for a while, plan its permitting, fuel and service from day one. Bring in your EPC and power specialists early, so generation and grid connection get engineered as one system.

The grid will catch up. Utilities and grid operators are investing heavily, and new transmission and generation are on the way. But that will take years, and the AI build-out isn’t waiting.

Speed to power is everything right now. The developers who win will be the ones who treat power as a core part of the development strategy from day one, not a constraint to solve later. If you’re thinking through what that could look like for your next project, give Wärtsilä a shout.

# # #

About the Author

Sean Hughes is a Business Development Manager at Wärtsilä Energy, focused on primary power for data centers in the U.S. market. He has 17 years of business development experience across the LNG and power generation industries and works with data center developers, operators and EPCs on power strategy, grid connection and on-site generation.